The contract is for a single supplier to act as the Principal Contractor and complete all works as follows:
- Stage 4 mechanical, electrical & civils design
- Enabling works for new steam & condensate return connections located on EC1 steam distribution and WBH.
- Supply and installation of steam and condensate equipment.
- Supply and installation of new steam connection & condensate return including all required equipment and associated civil & steelworks.
- Deliver a phased changeover of steam delivery from the WBH to the newly installed connection fed from EC1.
- Decommission, removal and disposal of WBH and associated redundant equipment.
- Disconnection and isolation of gas, compressed air and mains water.
- Commissioning and handover including Project Information Folder (PIF) is provided to the client Project Manager