Replacement of Public Rights of Way foot bridge. The former bridge had to be removed at short notice on health & safety grounds and is required to meet our statutory duty in relation to Public Rights of Way, where the footpath crosses the River Ouse. Due to the length of the bridge, we require a bespoke bridge consisting of metal beams rather than use one of our normal timber bridge kits so we need to use an approved supplier for metal bridges. Considerable time constraints - The Council has a window of the 15th June -1st October 2026 in which to install the bridge.
| Lot | Title | Value |
|---|---|---|
| 1 | Lot 1 | — |
| Title | Supplier | Value | Awarded |
|---|---|---|---|
| Award 1 | CTS BRIDGES LIMITED | — | — |