Arbroath Harbour Replacement of dock gates 2026
AwardHighlights
- Award value
- £806,521
- Winning supplier
- BigCat Contracts
- Award date
- 10 Aug 2026
Details
- Published
- 10 Aug 2026
- Deadline
- —
- Value
- £806,521
- Location
- UKM71
- Source
- Public Contracts Scotland
- Source notice ID
- rls-70-AUG562005
- OCID
- ocds-r6ebe6-0000830625
- CPV codes
- 45241000
Description
The existing dock gates have come to the end of their serviceable life and require to be replaced.
The dock gates were installed in 2004 are created the marina area with a maintained water level.
The current dock gates will have to be removed and replaced with new. The works will include temporary works to create a dry working area and to sustain the water levels within the marina.
Similar opportunities
- BCU-ITT-64089 - North Wales Medical School - West (YG)TenderBetsi Cadwaladr University Health BoardCloses 19 Oct 2026
- BCU-ITT-64088 - NORTH WALES MEDICAL SCHOOL - CENTRAL (YGC)TenderBetsi Cadwaladr University Health BoardCloses 15 Oct 2026
- Liversedge and Settle RoofTenderYorkshire Housing LimitedCloses 18 Sept 2026
- Forest Infrastructure Construction & Maintenance Framework 2027TenderNatural Resources WalesCloses 21 Oct 2026
- Relocation of Thorne Moors Viewing TowerTenderNatural EnglandCloses 15 Oct 2026
More from Angus Council
View all- Provision of Insurance Claims Management SoftwareAwardAngus CouncilAwarded £15,068
- Framework Agreement for Recycled Domestic Furniture and Strater Pack GoodsAwardAngus CouncilAwarded
- Tender for the Supply of Local Bus Services for June 2026AwardAngus CouncilAwarded
- Award of National Cycle Network Route 1, Angus – Active Travel Scheme Feasibility and DesignAwardAngus CouncilAwarded £15,000
- Award of National Cycle Network Route 1, Angus – Active Travel Scheme Feasibility and DesignAwardAngus CouncilAwarded £15,000
Lots (1)
| Lot | Title | Value |
|---|---|---|
| 1 | The existing dock gates have come to the end of their serviceable life and require to be replaced. The dock gates were installed in 2004 are created the marina area with a maintained water level. The current dock gates will have to be removed and replaced with new. The works will include temporary works to create a dry working area and to sustain the water levels within the marina.The existing dock gates have come to the end of their serviceable life and require to be replaced. The dock gates were installed in 2004 are created the marina area with a maintained water level. The current dock gates will have to be removed and replaced with new. The works will include temporary works to create a dry working area and to sustain the water levels within the marina. | — |
Awarded contracts (1)
| Title | Supplier | Value | Awarded |
|---|---|---|---|
| Award ocds-r6ebe6-0000830625-1 | BigCat Contracts | £806,521 | 10 Aug 2026 |