CAS-01336-R8D9H5 - GARAGE BLOCK Flats 1-12 Gablehurst, Upton, Poole, BH16 5JA - Roofline Renewal

Award

ASTER GROUP LIMITED

Highlights

Award value
Winning supplier
SPR Roofing Contractors Ltd
Award date

Details

Published
31 Jul 2026
Deadline
Value
Location
Source
Find a Tender
Source notice ID
072476-2026
OCID
ocds-h6vhtk-06d848
CPV codes
View on Find a Tender

Description

Project: The refurbishment of the main hipped roof

  • NB: All roofing work to be carried out by an NFRC accredited contractor & must be

able to self-certify via the competent roofing scheme.

  • As part of contractor pre-survey, contractor should identity any soffit and live extractor fan vents

which will need to be disconnected and reconnected during works

  • Temporarily close off working areas to exclude vehicles and pedestrians from the site using

suitable signage and remove them upon the re-opening on completion of the works.

  • Provide scaffolding/staging as required to the properties to enable safe access to undertake

all works outlined within the schedule in accordance with Working at Height Regs. 2005. All

scaffolding is to be erected, managed and dismantled in accordance with guidance of NASC -

SG4 and Design should be in accordance with NASC - TG20:21.

  • Allow to remove existing roof covering in accordance with current asbestos management

guidelines clearing all resultant debris from working area before starting to build and fix the

ladders, fit the deck and install new plastics as per the pricing document

Page 5 of 15

  • The contractor shall review the asbestos R&D supplied and manage a

specialist asbestos removals contractor to undertake the removal and disposal of

any hazardous waste material.

  • Ensure that the removal of the existing roof covering including ACM sheets and all

plastics inc guttering is compliant with current regulations.

The removals contractor must have UKATA/IATP training qualifications for any unlicensed

removals and provide consignment note upon completion of works.

  • Make and supply “ladders” fitted over concrete beams to provide fall of at least 5 degrees to

the rear of the garages

  • Remove the all existing, soffits, facia and guttering including any associated fixtures

and install the deck or waterproof covering with associated fixtures & fittings

  • Install new fascia around the building to conceal the roof ladders as well deepflow gutter

with appropriate clips and fittings to the rear. Also supply and fit appropriate downpipe,

with appropriate clips and fittings, to the rear of the property with a minimum 2 down pipes

and all clips to be a maximum 1 metre apart

More from ASTER GROUP LIMITED

View all

Lots (1)

LotTitleValue
1Lot 1

Awarded contracts (1)

TitleSupplierValueAwarded
Award 1SPR Roofing Contractors Ltd
R8D9H5 - GARAGE BLOCK Flats 1-12 Gablehurst, Upton, Poole, BH16 5JA -… | Winston Scout