Engineering Stage 5 (ES5) and Enabling Works for upgrade to Witton and Aston Rail Stations

Award

West Midlands Combined Authority

Highlights

Award value
£4,221,520
Winning supplier
Network Rail Infrastructure
Award date
30 Oct 2026

Details

Published
5 Nov 2026
Deadline
—
Value
£4,221,520
Location
—
Source
Find a Tender
Source notice ID
105286-2026
OCID
ocds-h6vhtk-07b40a
CPV codes
—
View on Find a Tender

Description

The upgrade of Witton and Aston stations was identified as a Mayoral priority in April 2025, with delivery of the interventions to be completed ahead of the UEFA Euro 2028, which nearby Villa Park Stadium is set to host four international football matches.

We are now proposing to continue the development phase into Engineering Stage 5 with Network Rail and in parallel commence advanced enabling works activities ahead of a targeted completion ahead of UEFA Euro 2028.

Design Development

The project has proceeded through design stages ES3 and ES4 and now needs to progress to detailed design. This is Engineering Stage 5 (ES5) in Network Rail's PACE framework. Additional elements for the next design phase include Overhead Line Equipment (OLE) isolation works to minimise disruption to the network in advance of the enabling works and core construction work phases, preliminary / personnel costs, contingency, and property and planning costs associated with the Waterworks site.

Enabling Works Need

To achieve programme and completion in advance of UEFA Euro 2028, enabling works are required in parallel to ES5 (detailed design) development.

More from West Midlands Combined Authority

View all

Lots (1)

LotTitleValue
1Lot 1—

Awarded contracts (1)

TitleSupplierValueAwarded
Engineering Stage (ES5) and Enabling Works for Witton and Aston Rail StationsNetwork Rail Infrastructure£4,221,52030 Oct 2026