Fire Compliance Building Work

Award

CELL THERAPY CATAPULT LIMITED

Highlights

Award value
Winning supplier
ALERON FIRE PROTECTION LIMITED
Award date

Details

Published
14 Jul 2026
Deadline
Value
Location
Source
Find a Tender
Source notice ID
066499-2026
OCID
ocds-h6vhtk-06cb6c
CPV codes
View on Find a Tender

Description

The works relate to fire compliance within CGTC MIC Braintree Building 2, which must be completed before the building can be brought into operational use. The scope of works is required to ensure compliance with statutory fire safety requirements and to enable the safe occupation of the building.

Contract term is from 20-Jul-2026 to 26-Oct-2026 at £263,906.28 (excluding VAT).